August 13, 2002
Colorado DOT Approves Unsolicited HOT Lane Offer by Public Works FinancingColorado’s Transportation Commission on June 20 approved an unsolicited
proposal from an equal venture of HBG Flatiron and Fluor Daniel for
public-private development of four new high-occupancy toll (HOT) lanes in the
median of C-470 between I-25 and I-70, in southwest Denver.
F&F Infrastructure Inc.’s proposal includes preliminary design, financing
(non-recourse toll revenue bonds issued by a private, not-for-profit company
or a new statewide toll agency recently authorized by the state legislature),
design-build construction, and toll facilities and roadway operations and
maintenance for the HOT lanes. The project’s conceptual design-build estimate
is $315 million.
|