FETC - ORANGE COUNTY, CALIFORNIA  
Back to Highways
Name Foothill / Eastern Transportation Corridor Agency (FETCA)
Location Orange County, California
Mode Toll Highway
Description

New public toll facility being constructed by TCA

Comprised of two principal segments:

Eastern Transportation Corridor (24-mile)
Foothill Transportation Corridor (27.7-mile upon completion)

Provides direct access between Riverside County's residential areas and Orange County's southeastern suburbs and northern San Diego County.

Initially constructed with two to three lanes initially in each direction with auxiliary climbing lanes, with future expansion capacity in the median available for general purposes, HOV lanes, or transit use.

Sponsor Foothill / Eastern Transportation Corridor Agency (FETCA) -- formed in 1986 to plan, finance, construct and operate Orange County's 52-mile public toll road system.
Cost $1.5 billion ($750 million in construction)
Type of Finance $25 million standby construction contingency line of credit via TE-045
$120 million standby federal line of credit, available for a ten-year period upon completion of each facility, is intended to provide limited supplemental capital in the event that traffic shortfalls arise with an adverse impact on revenues (impairing debt service coverage) during the ramp-up phase.
$1.263 billion from fixed rate revenue bonds
$246 million from variable rate revenue bonds
$67 million California State and Local Transportation Partnership Program Funds
Interest earnings on bond proceeds
Development Impact Fees
Subordinated vendor financing available, if needed
Revenue Sources Tolls, Development Impact Fees, Interest Earnings
Project Delivery / Contract Method

Design-build consortium; turnkey; design-bid-build; guaranteed maximum price and completion date.

Private Investor Partner Design-build consortium
Project Advisors Nossaman, Guthner, Knox & Elliott, LLP
Lead Underwriters J.P Morgan (Initial Issuance, 1995)
Saloman Smith Barney (Initial Issuance, 1995)
Paine Webber (Initial Issuance, 1995)
Saloman Smith Barney (Refunding 1999)
Letter of Credit Bank Morgan Guaranty Trust Co.
Physical Status Eastern Corridor and northern section of Foothill Corridor are open to traffic and performing above projections.Southern Foothill Corridor in environmental document development phase.
Financial Status Refinanced 1999
Innovations Design/Build contract terms; securitizing Development Impact Fee stream as a stand-alone financing source; electronic toll collection.
Related Links / Articles

Moody's Credit Rating*
FITCH Credit Report for 1999 Bond Issues**

http://www.thetollroads.com
http://www.fhwa.dot.gov/innovativefinance/appd_04.htm

Contacts Transportation Corridor Agencies
125 Pacifica, Suite 100
Irvine, CA - 92618-3304
TEL (949)754-3400
FAX (949)754-3467
Last Review/Update Transportation Corridor Agencies, December 2003

THE AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, PBCONSULT, AND MOODY'S HEREBY EXPRESSLY DISCLAIM ALL EXPRESS, IMPLIED AND STATUTORY WARRANTIES OF ANY KIND AND MAKES NO REPRESENTATION OR WARRANTY, EXPRESS OR IMPLIED, TO ISSUER, ANY USER OR ANY OTHER PERSON OR ENTITY, AS TO THE ACCURACY. TIMELINESS, COMPLETENESS, TRUTHFULNESS, MERCHANTABILITY OR FITNESS FOR ANY PARTICULAR PURPOSE OF ANY DATA PROVIDED BY MOODY'S TO ISSUER PURSUANT HERETO.

** Each Report is derived from sources believed to be accurate and reliable. EACH REPORT IS PROVIDED "AS IS" WITHOUT WARRANTY OF ANY KIND AND FITCH, INC., AASHTO, and PBCONSULT MAKE NO REPRESENTATION OR WARRANTY, EXPRESS OR IMPLIED, AS TO THE ACCURACY, TIMELINESS, COMPLETENESS, MERCHANTABILITY OR FITNESS FOR ANY PARTICULAR PURPOSE OF ANY REPORT. Under no circumstances shall Fitch, AASHTO, or PBConsult have any liability to any person or entity for (a) any loss or damage in while or in part caused by, resulting from, or relating to, any error or other circumstance or contingency within or outside the control of Fitch or any of its directors, officers, employees or agents in connection with the procurement, collection, compilation, analysis, interpretational editing, transcription, transmission, communication, publication or delivery of any Report, or (b) any direct, indirect, special consequential, compensatory, or incidental damages whatsoever (including without limitation, lost profits).